CommercialGamingLarge Scale

Major California Entertainment Resort

How comprehensive analysis prevented a $62M estimation error

Project Value
$200M+
Multi-phase
Documents
800+
Drawing pages
Scope
Gaming
Hospitality + Entertainment
Location
Northern
California

The Challenge

A major Northern California entertainment and gaming resort project presented significant estimation challenges that threatened the accuracy of the bid submission.

Massive document set800+ pages across multiple disciplines (Architectural, Structural, MEP, Civil)
Tight deadlineCompressed timeline for bid submission with no room for errors
Complex coordinationMultiple subcontractor scopes requiring precise alignment
Specialized systemsComplex MEP systems for gaming floor environmental requirements

The Discovery

OBDNC's expert team conducted a thorough multi-discipline review that uncovered critical discrepancies that would have resulted in a catastrophic $62M+ cost overrun.

Comprehensive Document Review

OBDNC's expert estimators analyzed 800+ pages of construction drawings, leveraging advanced tools to coordinate review across architectural, structural, mechanical, electrical, and plumbing documents simultaneously.

Critical Discrepancies Detected

Expert analysis identified scope gaps between architectural and structural drawings where load-bearing requirements for gaming floor equipment were not properly coordinated, potentially requiring costly structural reinforcement mid-construction.

Duplicate Quantities Found

System-wide analysis revealed duplicate quantities in mechanical systems where HVAC components appeared in both general mechanical schedules and gaming floor specialty systems, leading to double-counting of major equipment costs.

Cross-Discipline Validation

Thorough cross-discipline coordination identified misalignments in electrical distribution systems serving gaming equipment, preventing significant rework during installation.

Total Potential Error Identified
$62M+
in misallocated costs and scope gaps

The Result

Corrections were made before bid submission, preventing significant financial exposure and project delays.

Cost Accuracy Achieved

Client avoided $62M+ in potential cost overruns, maintaining project profitability and competitive positioning in the bid process.

Bid Confidence Restored

Comprehensive validation provided team confidence in bid accuracy, enabling aggressive but realistic pricing strategy.

Timeline Maintained

Rapid AI analysis allowed corrections within bid deadline, avoiding costly extensions or missed opportunities.

Risk Mitigation

Early detection of scope gaps prevented mid-construction conflicts and change orders that would have impacted schedule and budget.

Return on Investment
31,000%
For every $1 spent on OBDNC OS analysis, the client saved $310 in avoided costs

Key Takeaways

1

Expert Analysis Delivers Precision

Comprehensive review of 800+ pages by experienced estimators, supported by advanced tools, identified critical discrepancies that would have been missed in traditional rushed reviews.

2

Cross-Discipline Coordination is Critical

Most errors occur at discipline interfaces. OBDNC's systematic approach to multi-trade coordination revealed gaps invisible to siloed reviews.

3

Early Detection Saves Exponentially

Finding errors at bid stage costs pennies compared to discovery during construction. The $62M in avoided costs represents the true value of pre-construction intelligence.